Owner: NV Energy
Customer: Shaw Group
Location: Las Vegas, NV
Duration: September 2010 – June 2011

Scope of Work: Summit Contracting was responsible for the non-heat-traced piping and equipment for NV Energy’s 484-Megawatt combined cycle system. At peak of construction, 750 workers were employed on this project. Summit logged 64,000 man-hours and insulated 17,000 lineal feet of piping meeting every schedule milestone.